Schedules run more than once

Having created a number of schedules I am finding that some schedules will run more than once. The schedule will complete successfully and immediately restart itself.

Anyone have any ideas?

Re: Schedules run more than once

Go to Exception Handling.

If your schedule takes ages to complete then CRD will treat it as "failed" after x time. Then it will re-run it y times.

Increase the "Treat as failed" time to about 1.5 times the time it normally takes the schedule to execute successfully.